Indicative Timeline
Garden Square Consultation
>
Indicative Timeline
An indicative timeline showing the key stages in the redevelopment of Garden Square Shopping Centre, Letchworth. The programme outlines how the project is expected to progress — from consultation and design through to construction and completion:
Public Consultation 1
December 2025
01
Public Consultation 2
Jan/Feb 2025
02
Planning Application Submission
Feb/March 2026
03
Planning Application Determined at Committee
June/July 2026
04
Construction Start on Site
May 2027
05
First residents move in
May 2029
06